Line 7 Warszawa Wawer – Otwock (four tracks)

under constructionstage: construction
PLN 1.4 billion
contract value · data from 14 Oct 2025net of VAT≈ PLN 1.4 billion (value-by-stage, est., nominal)funding: EU funds

Stage IIb of the modernisation of railway line no. 7 Warszawa Wschodnia Osobowa – Dorohusk, the last section of the route to Lublin. Between Warszawa Wawer and Otwock two new tracks of line no. 506 will be added, giving a four-track layout. The scope includes rebuilding Warszawa Falenica station and seven stops, four grade-separated crossings and 20 pedestrian underpasses. The contract with the Trakcja, Intop and Intop Warszawa consortium was signed on 14 October 2025. PLK puts its value at about PLN 1.4 billion net, and Sektor Kolejowy at about PLN 1.6 billion gross. The total project value in the grant agreement is PLN 2,082 million, of which the grant is PLN 1,432 million. Preparatory works were under way in February 2026, and completion is planned for 2028.

How it went

We have assessed this project, but none of the four axes is shown here: 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Construction startOct 2025
  2. Current date2028

Significance

Separating suburban from long-distance traffic will raise the capacity of the Otwock line, one of the busiest in the Warsaw Railway Node. After the investment the journey from Warsaw to Lublin is to take about 90 minutes. Train traffic between Wawer and Otwock was due to stop completely for the main works in April 2026. Koleje Mazowieckie and SKM were to run replacement buses.

Sources 4 · 4 independent

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. PKP Polskie Linie Kolejowe S.A.14 Oct 2025
    CostConstruction start
    CostDzisiaj podpisaliśmy umowę z wykonawcą inwestycji, która będzie realizowana za ok. 1,4 mld zł netto
    Construction startDzisiaj podpisaliśmy umowę z wykonawcą inwestycji
  2. Centrum Unijnych Projektów Transportowych
    InvestorFunding
    InvestorBeneficjent: PKP Polskie Linie Kolejowe S.A.
    FundingDofinansowanie: 1 431 965 109,75 PLN
  3. Rynek Kolejowy25 Feb 2026
    StatusStage
    Status · StagePKP PLK prowadzą roboty przygotowawcze do modernizacji linii między Wawrem a Otwockiem.
  4. Sektor Kolejowy14 Oct 2025
    Current date
    Current datePrace rozpoczną się jeszcze w 2025 r., a ich zakończenie planowane jest na 2028 r.