A nationwide electronic toll system for trucks and buses, built by a consortium led by Kapsch TrafficCom. GDDKiA named it the winner of the tender in October 2010 and the contract was signed in November 2010. The system has operated since 1 July 2011, at first on 1,560 km of roads. According to the operator, Kapsch Telematic Services, State Treasury outlays came to PLN 1,129 million, of which PLN 963 million went on building the system in 2011. The operating data come from July 2016.
How it went
We have assessed this project, but none of the four axes is shown here: 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section
Timeline
- Construction startNov 2010
- Original dateJul 2011
- DeliveryJul 2011
Significance
According to the operator, the system recovered its build outlay after 18 months, and revenue over the first five years was PLN 6,332 million. The tolled network grew from 1,560 km to 3,145 km by 2016.
Sources 3 · 3 independent
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- money.pl5 Jul 2016StatusStageCostDelivery
Status · DeliveryviaTOLL obowiązuje w Polsce od 1 lipca 2011 roku.
StageW systemie viaTOLL zarejestrowanych jest aktualnie ponad 910 tys. pojazdów o DMC powyżej 3,5 tony
CostNakłady inwestycyjne Skarbu Państwa to 1 129 mln zł, z czego 963 mln zł to nakłady poniesione na budowę systemu w 2011 r.
- ERTICO Newsroom25 Nov 2010Construction startOriginal date
Construction startKapsch TrafficCom signs contract for implementation and operation of the nation-wide tolling system in Poland.
Original datethe consortium led by Kapsch shall initially implement an extensive modern electronic toll solution on the existing road network of about 1.750 km until 1 July 2011
- Vindobona4 Oct 2010Investor
Investorthe Polish highway and road authority (GDDKiA) has declared the consortium led by Kapsch TrafficCom as winner of the tender.