S52 Northern Krakow Bypass with tunnels

completedstage: operationaldelivered
PLN 1.4 billion
contract value · data from 13 Nov 2018net or gross: not recorded≈ PLN 1.4 billion (value-by-stage, est., nominal)funding: EU fundsValue of the design-and-build contract with the Gulermak and Mosty Łódź consortium. In 2022 GDDKiA put the total investment cost, including supervision and land purchase, at PLN 1,671 million.

The eastern section of the Northern Krakow Bypass on the S52, from the Modlnica interchange to the Mistrzejowice interchange, is 12.3 km long with three lanes in each direction. GDDKiA signed the design-and-build contract on 13 November 2018 with the Gulermak and Mosty Łódź consortium for PLN 1,427,968,500. Construction began in July 2020 and the road opened on 23 December 2024, more than two years later than planned in 2018. The route has two tunnels, 653 m and 496 m long. In 2022 GDDKiA put the total investment cost, including supervision and land purchase, at PLN 1,671 million.

How it went

Assessment: settled, as of 23 Dec 2024. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

No source calls this a delay and the card makes no assessment here, but the dates recorded on this project differ by 2 years: originally 2022, currently 2024-12-23.

Deliverydelivered[3]
Utilisationin use[3]

Timeline

  1. Construction startJul 2020
  2. Original date2022
  3. Delivery23 Dec 2024

Change history

  • 23 Dec 2024stage: operational
  • Jul 2020stage: construction

Significance

The road links the exits of national roads DK79 and DK94 on the northern side of Krakow with the A4 and the S7, and is meant to take over through traffic and part of city traffic. The project produced 27 bridge structures with a combined length of almost 1.9 km and 23 retention reservoirs. The opening date moved from the turn of November and December 2024 because of contractor claims linked to archaeological work and rainfall.

Sources 5 · 5 independent

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. GDDKiA26 May 2022
    CostConstruction start
    Costpodpisaliśmy umowę na projekt i budowę S52 Północnej Obwodnicy Krakowa z konsorcjum firm: tureckiej Gulermak i polskiej Mosty Łódź, które wyceniły koszt zadania na 1 427 968 500 zł
    Construction startBudowa S52 Północnej Obwodnicy Krakowa rozpoczęła się w lipcu 2020 r.
  2. Radio Kraków26 May 2022
  3. Dziennik Warto Wiedzieć27 Dec 2024
    StatusStageDeliveryInvestorFundingUtilisation
    Status · Delivery · InvestorGeneralna Dyrekcja Dróg Krajowych i Autostrad udostępniła 23 grudnia 2024 r. do ruchu 25 km nowych tras
    Stage · Delivery · UtilisationUdostępniony do ruchu wschodni odcinek Północnej Obwodnicy Krakowa o długości 12,3 km
    FundingTrasa S52 otrzymała 789,6 mln zł dofinansowania ze środków Programu Operacyjnego Infrastruktura i Środowisko.
  4. Inżynieria.com27 Nov 2024
  5. WNP.pl21 Sep 2018
    Original date
    Original dateBudowa drogi ma zakończyć się w 2022 roku.