Design and construction of a section of the S19 expressway between Lutcza and the Domaradz interchange, about 6.4 km long, under a design-and-build contract. The contract with Kolin Insaat Turizm Sanayi ve Ticaret was signed in May 2024 and is worth PLN 1,416,239,220. The main structure is a twin-tube tunnel under Hyb hill, 924 m long, driven with the NATM method. The ZRID permit application was filed on 11 December 2025, which was late. The voivode's proceedings have run since the end of March 2026, and physical progress of the contract was 5 per cent in September 2026. Completion of the whole section is planned for May 2030.
How it went
We have assessed this project, but none of the four axes is shown here: 4 carry no assessment yet. The timeline and sources below show what is known about it. How to read this section
Timeline
- Construction startMay 2024
- Current dateMay 2030
Significance
The Domaradz interchange with a section of almost a kilometre is to be ready as early as 2027, so that the neighbouring Domaradz – Krosno section can open sooner. Domaradz will also get a road maintenance depot with a Tunnel Management Centre serving all S19 tunnels in Podkarpackie. A temporary link to the DK19 road in Lutcza is planned until the Jawornik – Lutcza section is built.
Sources 7 · 6 independent
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- GDDKiA, serwis inwestycjiConstruction startCurrent dateInvestor
Construction startData rozpoczęcia Data: 28.05.2024
Current dateData ukończenia odcinka 1 (53 m-cy bez okresów zimowych) Data: 29.05.2030
InvestorPrzedmiotem zamówienia jest zaprojektowanie i budowa drogi ekspresowej S19 na odcinku Lutcza-w. Domaradz (z węzłem) dł. ok. 6,43 km.
- Interia Motoryzacja31 May 2024Cost
CostUmowa opiewa na 1 416 239 220 zł.
- Krosno11211 Dec 2025
- toRzeszow.pl13 Dec 2025
- Inżynieria.com30 Sep 2026StatusStage
StatusW ostatnim tygodniu kontynuowano też opracowywanie projektów technicznych i wykonawczych dla części drogowej, mostowej i tunelowej
StageOd końca marca 2026 r. Wojewoda Podkarpacki prowadzi postępowanie w sprawie wydania decyzji o zezwoleniu na realizację inwestycji drogowej (ZRID) dla odcinka S19 Lutcza–Domaradz.
- Rynek Infrastruktury11 Dec 2025
- Interia Motoryzacja6 May 2026