🚆Transportstrategic

S19 Dukla – Barwinek (state border)

under constructionstage: construction
PLN 1.5 billion
contract value · data from 10 Oct 2022net or gross: not recorded≈ PLN 1.5 billion (value-by-stage, est., nominal)Limitations: the amount recorded at the current stage, nominal, not adjusted for inflation. The total cost of the project may differ.

Construction of an 18.2 km section of the S19 expressway from Dukla to the Slovak border at Barwinek, under a design-and-build contract. The contract with Polaqua was signed on 10 October 2022 and is worth about PLN 1.54 billion. The scope includes the Barwinek interchange, 15 viaducts, bridges, overpasses and wildlife crossings. The ZRID permit was issued in July 2025. In October 2026 earthworks and the casting of viaduct supports are under way, and the contract completion date is 4 May 2027.

How it went

No outcome assessment on this card. This is not a fault: we show an assessment only where a source quote stands behind it. Of the four axes, 4 carry no assessment yet. The timeline and sources below show what is known about the project. How to read this section

Timeline

  1. Current dateMay 2027

Significance

This is the last Polish S19 section before the Slovak border. The terrain has complex geology, with 19 landslide and landslide-prone areas. The longest viaduct is to be about 1.1 km. GDDKiA states that the section is co-financed from the Connecting Europe Facility.

Sources 4 · 4 independent

Every fact on this card comes from the sources below. Next to sources with a quote you can see which fields they support.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. GDDKiA (gov.pl)2 Nov 2026
    Current date
    Current dateZakończenie robót wynikające z umowy 4 maja 2027 r.
  2. Auto Świat10 Oct 2022
    CostInvestor
    CostWybudowanie przygranicznego fragmentu trasy Via Carpatia pochłonie 1,54 mld zł.
    InvestorGDDKiA podpisała umowę z wykonawcą nowego fragmentu Via Carpatii.
  3. Forsal.pl7 Jul 2025
  4. Krosno11221 Oct 2026
    StatusStage
    Statusbetonowane są filary i przyczółki.
    StageNajbardziej zaawansowane prace widoczne są w Dukli przy obiekcie ES-2/4, gdzie trwa budowa podpór i przyczółków przyszłej estakady