S19 Domaradz – Krosno (Iskrzynia)

pausedstage: tender
PLN 1.1 billion
contract value · data from 27 Jul 2022net or gross: not recorded≈ PLN 1.1 billion (value-by-stage, est., nominal)

A 12.5 km section of the S19 expressway between the Domaradz and Krosno (Iskrzynia) interchanges, procured as design-and-build. The contract with Mostostal Warszawa was signed on 7 November 2022 on the basis of a bid of PLN 1,063,251,940.57, and works were due to finish at the end of 2026. Physical progress was 13 per cent in May 2026. In April 2026 Mostostal withdrew from the contract for reasons it attributes to the contracting authority. GDDKiA treated that withdrawal as ineffective and in May 2026 terminated the contract itself, citing the contractor's fault. A tender to complete the section was announced in early September 2026, with bids due on 12 October.

How it went

We have assessed this project, but none of the four axes is shown here: 4 carry no assessment yet. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Original dateDec 2026

Significance

The section links the Domaradz interchange with the Krosno area on the S19 between Rzeszów and Barwinek. The new contractor is to have 29 months for design and construction, and the project already holds a ZRID permit. The scope includes demolition and assessment of unaccepted works by the previous contractor. Mostostal says that changes after the environmental decision required lengthening structures by more than 700 m, with the extra works estimated at about PLN 550 million. GDDKiA does not accept those changes.

Sources 6 · 5 independent

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. conadrogach.pl27 Jul 2022
    Cost
    CostNajkorzystniejszą złożyła spółka Mostostal Warszawa, która zaoferowała zrealizowanie tego odcinka Via Carpatia za kwotę 1 063 251 940,57 zł.
  2. Parkiet (komunikat ESPI)2 Apr 2026
  3. Forsal.pl14 May 2026
    StatusInvestor
    Status · InvestorGDDKiA zerwała umowę z Mostostalem Warszawa na budowę odcinka S19 Domaradz – Krosno (Iskrzynia)
  4. Auto Świat2 Sep 2026
    Stage
    StageGDDKiA ogłosiła przetarg na dokończenie budowy drogi ekspresowej S19 na odcinku pomiędzy węzłami Domaradz i Krosno.
  5. Interia Motoryzacja6 May 2026
  6. conadrogach.pl14 Mar 2024
    Original date
    Original datewszystkie prace na odc. S19 Krosno – Domaradz powinny zostać ukończone z końcem 2026 roku