Construction of an 11.6 km section of the S19 expressway between Babica and Jawornik along Via Carpatia, under a design-and-build contract. The contractor is Przedsiębiorstwo Usług Technicznych Intercor and the contract is worth PLN 1.25 billion. The best-known structure is the eight-span ES-26 viaduct, 1,082 m long with piers up to 80 m, the tallest in Poland. Progress passed 80 per cent in August 2026. The completion date, originally September 2026, has moved to the fourth quarter of 2027 because of geological conditions that differed from the assumptions and bad weather.
How it went
We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section
Timeline
- Construction startAug 2023
- Original dateSep 2026
- Current dateDec 2027
Change history
- Aug 2023stage: construction
Significance
The section completes another stretch of the S19 expressway south of Rzeszów in the international Via Carpatia corridor. The ES-26 deck sits about 120 m above the valley floor and the longest cantilever span is 188 m. The delay of more than a year is attributed to geology and weather, and the contract annexes are still being processed.
Sources 3 · 3 independent
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Inżynier Budownictwa30 Aug 2023StageCostConstruction startOriginal date
Stage · Construction startS19 Babica–Jawornik wkracza w fazę budowy.
CostWartość umowy wynosi 1 253 370 000 zł.
Original dateprace projektowe i roboty budowlane wraz z uzyskaniem pozwolenia na użytkowanie zostaną ukończone w ciągu 43 miesięcy, tj. we wrześniu 2026 r.
- RMF2427 Aug 2026StatusInvestor
Statusstan zaawansowania prac na odcinku przekroczył 80 proc.
Investorkierownik projektu z ramienia GDDKiA w Rzeszowie
- Carpatia Biznes28 Aug 2026Current date
Current dateObecnie termin oddania trasy do użytkowania przewidywany jest na IV kwartał 2027 roku.