S11 Przygodzice – Kępno Północ (Ostrzeszów)

in preparationstage: permits
PLN 1.1 billion
contract value · data from 22 Jul 2025net or gross: not recorded≈ PLN 1.1 billion (value-by-stage, est., nominal)

Construction of about 31 km of the S11 expressway in southern Wielkopolska, under two design-and-build contracts: Przygodzice – Ostrzeszów Północ (12.6 km, Mirbud, over PLN 549.4 million gross, signed 21 July 2025) and Ostrzeszów Północ – Kępno Północ (almost 18 km, Budimex, PLN 588,232,566.40). The building designs are ready and the ZRID applications were filed with the voivode in April and May 2026. Site work is to start once the decisions are issued and last 22 months, with a winter break. Opening is planned for 2029.

How it went

We have assessed this project, but none of the four axes is shown here: 4 carry no assessment yet. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Construction startJul 2025
  2. Current dateDec 2029

Significance

The new sections extend the existing S11 from the Ostrów Wielkopolski bypass to Kępno. Przygodzice – Ostrzeszów Północ includes the Przygodzice and Antonin interchanges (a link to the DK25 road towards Oleśnica and Wrocław) and four wildlife crossings. Ostrzeszów Północ – Kępno Północ bypasses Ostrzeszów to the west and has three interchanges and 16 engineering structures.

Sources 6 · 4 independent

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Forsal25 Mar 2025
  2. EurobuildCEE22 Jul 2025
    Cost
    CostWartość kontraktu to ponad 549,4 mln zł brutto.
  3. Interia Motoryzacja22 Jul 2025
    Current date
    Current datePlanowany termin oddania trasy do użytku to druga połowa 2029 roku.
  4. Auto Świat22 May 2026
    StatusStageConstruction startInvestor
    StatusW ciągu dziesięciu miesięcy od podpisania umowy wykonawca przygotował projekt budowlany i zgodnie z harmonogramem złożył wniosek o wydanie decyzji ZRID.
    StageDo wojewody wielkopolskiej GDDKiA złożyła właśnie wniosek o wydanie decyzji zezwalającej na realizację inwestycji drogowej (ZRID).
    Construction startUmowa na projekt i budowę tego odcinka S11 została podpisana 21 lipca 2025 r.
    InvestorGeneralna Dyrekcja Dróg Krajowych i Autostrad złożyła właśnie wniosek o pozwolenie na jego budowę.
  5. Auto Świat22 Jul 2025
  6. Auto Świat16 Apr 2026
    Cost
    CostZa realizację inwestycji odpowiada firma Budimex, która wykona prace za kwotę 588 mln 232 tys. 566 zł i 40 gr.