Expansion of Kraków Airport (New Investment Plan: Terminal Stage I + New Runway)

under constructionstage: construction
4.2 bn PLN
programme budget (multi-year) · data from Feb 2026net or gross: not recorded≈ 4.2 bn PLN (value-by-stage, est., nominal)

The New Investment Plan of Kraków Airport (John Paul II International Airport Kraków-Balice) comprises 19 tasks with a total value of approx. PLN 4.2 billion and is the largest expansion programme in the history of the Balice airport. A key element is the construction of a new part of the passenger terminal (T6) with an area of nearly 45,000 m², with 11 new gates, 54 passport control booths, and 20 ABC gates. The contract for the terminal expansion, worth PLN 537.7 million, was signed on 13 May 2026 with the contractor Mostostal Warszawa SA; the new part is planned to be brought into use in mid-2029. The plan also provides for the construction of a new runway and the modernisation of the apron and airfield infrastructure. All stages of the programme are to be completed by 2032.

How it went

We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Construction start13 May 2026
  2. Original date2032
  3. Current date2032

Change history

  • 13 May 2026stage: construction

Significance

The expansion is intended to address the overload of Kraków Airport – the second-largest airport in Poland and the largest regional one. After the new part of the terminal is brought into use (approx. 2029), the airport is to handle up to 16 million passengers per year, and after completion of all stages by 2032, more than 20 million. The new runway and modernisation of the apron are intended to remove the infrastructural barriers limiting further growth of traffic in Balice.

Sources 6 · 5 independent · 5 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Infrastruktury (gov.pl)13 May 2026
    StatusStageStage historyConstruction startOriginal dateCurrent dateInvestor
    Status · Stage · Stage history · Construction start13 maja 2026 r. podpisano umowę na rozbudowę terminalu pasażerskiego Kraków Airport
    Original date · Current dateDo 2032 r. zakończone zostaną wszystkie etapy rozbudowy terminalu
    InvestorMiędzynarodowy Port Lotniczy im. Jana Pawła II Kraków-Balice
  2. Obserwator Logistyczny13 May 2026
    LocationRozbudowa terminalu w Balicach ma kosztować 537,7 mln zł netto
  3. Architektura Murator Plus13 May 2026
  4. KRKnews10 Feb 2026
    Cost
    CostKraków Airport uruchamia Nowy Plan Inwestycyjny obejmujący 19 zadań o łącznej wartości ok. 4,2 mld zł.
  5. Funding
    FundingWe wrześniu ubiegłego roku Kraków Airport złożył wniosek o dofinansowanie realizacji inwestycji ze środków CEF Transport Military Mobility.