Gdańsk Airport Investment Programme 2025–2028

under constructionstage: construction
500 mln PLN
programme budget (multi-year) · data from Mar 2025net or gross: not recorded≈ 500 mln PLN (value-by-stage, est., nominal)

The investment programme of Gdańsk Lech Wałęsa Airport for the years 2025–2028 comprises a package of tasks with a total value of about half a billion złoty. Its most important elements include: expansion of the airfield together with a new PPS4/4A apron (ultimately 45 aircraft stands and three new de-icing stands, cost approx. PLN 105 million), expansion of the aircraft maintenance base (MRO, approx. PLN 80 million), construction of a second office building, Bravo, as part of Airport City Gdańsk (16,500 m² of rentable space, approx. PLN 180 million), and a carport with a photovoltaic installation carried out by Polimex Budownictwo. The individual components are being implemented in stages through 2028. Note on the figure: the PLN 500 million is the airport's own aggregate, repeated by the PAP wire; the four publicly itemised components (105 + 180 + 80 + 23 million) sum to PLN 388 million, and Trojmiasto.pl – reporting independently the same day – put the programme at "blisko 400 mln zł" (close to PLN 400 million). The ~PLN 110 million gap is work not itemised publicly.

How it went

We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Announced26 Mar 2025
  2. Original date2028
  3. Current date2028

Change history

  • 26 Mar 2025stage: announced

Significance

The programme is intended to increase the capacity and energy self-sufficiency of Poland's third-largest airport. The new apron and additional de-icing stands are to streamline air traffic handling, expansion of the MRO base strengthens the aircraft technical-servicing facilities, and the carport with photovoltaic modules is to reduce the airport's dependence on external energy supplies. The earlier expansion of Terminal T2 with a western pier enlarged the terminal area by nearly 16,000 m².

Sources 9 · 5 independent · 3 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Port Lotniczy Gdańsk im. Lecha Wałęsy26 Mar 2025
    CostStatusStageStage historyAnnouncedOriginal dateCurrent dateInvestor
    Cost · Original date · LocationW najbliższych czterech latach Port Lotniczy Gdańsk zainwestuje w lotnisko pół miliarda złotych.
    StatusW grudniu 2024 roku Port Lotniczy Gdańsk zawarł umowę na kompleksową realizację inwestycji carportu, czyli parkingu wraz z zadaszeniem, które zamiast tradycyjnego dachu będzie miało zamontowane moduły fotowoltaiczne.
    StageInwestycję zrealizuje firma Polimex Budownictwo, za 23 miliony złotych netto, do połowy 2026 roku.
    Stage history · Announced26.03.2025 | 14:00
    Current dateZostanie zrealizowana do 2028 roku, kosztem 105 milionów złotych.
    InvestorPort Lotniczy Gdańsk im. Lecha Wałęsy
  2. Gdańsk.pl26 Mar 2025
  3. Gdańsk.pl22 Jun 2022
  4. Inżynieria.com27 Mar 2025
    CostCurrent dateOriginal dateInvestor
    Cost · Current date · Original date · InvestorW latach 2025–2028 Port Lotniczy Gdańsk planuje inwestycje w lotnisko na poziomie 500 mln zł.
  5. Pasazer.com26 Mar 2025
    CostOriginal date
    Cost · Original dateDo 2028 roku na rozbudowę ma zostać przeznaczonych pół miliarda złotych.
  6. Trojmiasto.pl26 Mar 2025
    Investor
    InvestorW ciągu czterech lat port lotniczy w Gdańsku zainwestuje blisko 400 mln zł.
  7. WNP.PL26 Mar 2025
    CostOriginal dateAnnounced
    Cost · Original date · AnnouncedRzeczniczka gdańskiego lotniska Agnieszka Michajłow w środę przekazała, że w latach 2025-2028 na inwestycje przeznaczonych zostanie pół miliarda złotych.
  8. Pasazer.com20 Jul 2026
    Status
    StatusInwestycja ta będzie jednak opóźniona o około pół roku. Jest to efekt odwołania które wpłynęło i jest obecnie rozpatrywane przez Generalną Dyrekcję Ochrony Środowiska. Bez decyzji wydanej przez GDOŚ uzyskanie pozwolenia na budowę jest obecnie niemożliwe.
  9. Port Lotniczy Gdańsk im. Lecha Wałęsy18 Aug 2026