A1 Motorway Gdańsk–Toruń (Gdańsk Transport Company concession section)

completedstage: operationaldelivered
730 mln EUR
contract value · data from 2011net or gross: not recorded≈ 3.1 bn PLN (value-by-stage, est., nominal)funding: PPP (private financing by the concessionaire)

The northern, concession section of the A1 motorway, approximately 152 km long, running from Gdańsk (Rusocin) to Toruń, delivered under a public-private partnership formula by Gdańsk Transport Company S.A., which financed, designed, built, and operates the route (ultimately through 2039). The concession agreement with the government was signed in August 2004. The investment was carried out in two stages: Stage I Rusocin–Nowe Marzy (90 km, contract value EUR 529 million), whose first sections opened on 22 December 2007, and Stage II Nowe Marzy–Toruń (62 km, contract value EUR 730 million, including EUR 581 million for the road and EUR 149 million for bridge structures). Stage II was opened to traffic on 14 October 2011, completing the continuous motorway connection Gdańsk–Toruń ahead of the UEFA Euro 2012 European football championship. The figure in the cost field (EUR 730 million) refers to the Stage II contract (Nowe Marzy–Toruń), opened in 2011.

How it went

Assessment: settled, as of 19 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverydelivered[1]
Scheduleahead of schedule[2]

Timeline

  1. AnnouncedAug 2004
  2. Delivery14 Oct 2011

Change history

  • 14 Oct 2011status: completedThe opening to traffic of stage II (Nowe Marzy–Toruń) completed the concession section Gdańsk–Toruń.
  • 14 Oct 2011stage: operational

Significance

The completion in 2011 of the concession section Gdańsk–Toruń provided the first continuous motorway connection between the Tricity area and central Poland and shortened travel time between Gdańsk and Toruń to approximately 65 minutes. The route was one of the largest road investments delivered in Poland under a public-private partnership formula, and its completion ahead of UEFA Euro 2012 was significant for handling traffic for the tournament co-hosted by Poland. The concessionaire Gdańsk Transport Company S.A. manages the entire approximately 152 km section as a toll road until 2039, after which the facility is to be transferred to the public side.

Sources 6 · 3 independent · 6 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

A “wiki” mark means the value stands on Wikipedia alone. Our count of independent sources treats it as zero, so read such a place as less firmly documented than the rest of the card – that applies to an outcome row, a figure, a date and a status alike.

  1. AmberOne / Gdańsk Transport CompanyOct 2011
    StatusStageCostDelivery
    StatusW dniu 14 października 2011 roku, zostają oddane do użytku kolejne 62 kilometry
    Stage · DeliveryOddanie do eksploatacji drugiego etapu, prowadzonej przez nas inwestycji zakończyło ostatecznie realizację koncesyjnego odcinka autostrady A1
    CostCena budowy drugiego etapu inwestycji wyniosła 730 mln EUR, w tym 581 mln EUR/droga i 149 mln EUR/mosty
  2. NDI
    Schedule
    Schedule4,5 miesiąca przed terminem
  3. Wikipedia (pl)
    AnnouncedDelivery
    Announcedsierpień 2004 – podpisanie Umowy Koncesyjnej Etap 1
    Delivery14 października 2011 – oddanie do ruchu Etapu 2
  4. Wikipedia (pl)
  5. TerenyInwestycyjne.infoOct 2011
    Investor
    InvestorGdańsk Transport Company - spółka posiadająca koncesję na finansowanie, projektowanie, budowę oraz eksploatację tego fragmentu autostrady
    LocationTrasę pomiędzy Gdańskiem a Toruniem można pokonać już w 65 minut.
  6. Funding
    Fundingthe European Investment Bank, Nordic Investment Bank, and Swedish Export Credit Corporation, provided GTC with loans which covered 95% of the project’s demand for financing; the GTC Shareholders contributed the remaining 5%.
    FundingIn the motorway operation period, GTC receives availability payments from the National Road Fund.