Expansion of the Żelazny Most Mining Waste Disposal Facility – Southern Quarter

completedstage: operationaldelivered
1.0 bn PLN
programme budget (multi-year) · data from 2021net or gross: not recorded≈ 1.0 bn PLN (value-by-stage, est., nominal)

Construction of a new Southern Quarter as part of the Żelazny Most Mining Waste Disposal Facility (OUOW) – the largest tailings storage facility in Europe, owned by KGHM Polska Miedź. The expansion included preparatory works and the construction of dams surrounding the new quarter and was intended to ensure continuity of depositing waste from KGHM's mining and metallurgical chain for years to come. The investment was carried out by Budimex, and the facility was officially opened at the turn of 2021, seven months ahead of schedule despite the pandemic.

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet. How to read this section

Deliverydelivered[1]
Scheduleahead of schedule[6]
Utilisationin use[6]
post-flotation tailings deposited at the OUOW Żelazny Most (Southern Quarter operational since Q1 2021)
Current
~30 mln ton rocznie
Capacity or target
Kwatera Południowa: pojemność docelowa ~170 mln m³, eksploatacja planowana 2021–2042
Unit
mn tonnes/yr

Timeline

Ahead: under a year

  1. Delivery3 Nov 2021

Change history

  • 3 Nov 2021stage: operational

Significance

The expansion secures the continuity of depositing approx. 30 million tonnes of tailings per year, which is crucial for the uninterrupted operation of KGHM's entire mining and metallurgical chain. Together with the newly added Southern Quarter, the facility covers more than 2,000 ha, remaining the largest storage facility of its kind in Europe. A new method of building dams on the outside of the quarter was applied, intended to improve safety and environmental protection in the region of the Legnica-Głogów Copper District.

Sources 7 · 4 independent · 7 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Ministerstwo Aktywów Państwowych (gov.pl)3 Nov 2021
    StatusStageCostStage historyDelivery
    StatusSiedem miesięcy przed terminem ukończono rozbudowę
    StageKwatera Południowa Żelaznego Mostu KGHM oficjalnie otwarta
    CostWartość nowej inwestycji to ponad 1 mld zł.
    Stage history03.11.2021
    DeliverySiedem miesięcy przed terminem ukończono rozbudowę Obiektu Unieszkodliwiania Odpadów Wydobywczych Żelazny Most.
  2. KGHM Polska Miedź S.A. (biuro prasowe)3 Nov 2021
    DeliveryInvestor
    NameKwatera Południowa stanowiąca element Obiektu Unieszkodliwiania Odpadów Wydobywczych Żelazny Most to największa inwestycja KGHM Polska Miedź S.A. od 2018 roku
    TypeRozbudowa Obiektu, mimo pandemii została ukończona 7 miesięcy przed terminem
    Deliveryśroda, 03 listopada, 2021
    Investorto największa inwestycja KGHM Polska Miedź S.A. od 2018 roku
    LocationZlokalizowany na Dolnym Śląsku OUOW Żelazny Most
  3. Inżynieria.com8 May 2018
  4. Wikipedia (pl)
  5. KGHM Polska Miedź S.A. (biuro prasowe)2020
    Utilisation
    UtilisationDocelowa objętość Kwatery Południowej ma wynosić około 170 mln m³
  6. Inżynieria.com3 Nov 2021
    ScheduleUtilisation
    ScheduleNajwiększa inwestycja miedziowego giganta od 2018 r. została ukończona siedem miesięcy przed terminem
    UtilisationRocznie zostaje tu odprowadzonych około 30 mln ton odpadów