PAK CCGT Turek combined-cycle unit (ZE PAK, 562 MW)
A combined-cycle gas unit with a net installed capacity of 562 MW on the site of the former Adamów coal power plant in Turek, built by PAK CCGT of the ZE PAK Group. The contract with the Siemens Energy Global, Siemens Energy and Mytilineos consortium was concluded in September 2023 and construction began in December 2023. The estimated cost is about PLN 2.3 billion. Progress reached about 89 per cent at the end of the first half of 2026. The completion date has moved from the turn of 2026 and 2027 to the third quarter of 2027, so the unit will miss the capacity obligation due from January 2026.
How it went
We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section
Timeline
- Construction startDec 2023
- Original dateDec 2026
- Current dateSep 2027
Change history
- Dec 2023stage: construction
Significance
The unit won a capacity-market auction in December 2021 and holds a 17-year contract for 493 MW. ZE PAK estimates the capacity-market revenue lost to the delay at about PLN 16.4 million a month and the contractual penalty for 2026 at about PLN 1 million a month. The company says the unit can generate close to 5 TWh of electricity a year.
Sources 5 · 5 independent
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- LM.pl21 Nov 2023CostOriginal date
CostSzacunkowy koszt inwestycji to ok. 2,3 mld zł.
Original dateoddanie elektrowni do eksploatacji przewidziane jest na przełom 2026 i 2027 roku
- WysokieNapiecie.pl (ISBnews)2 Jan 2026StageConstruction startCurrent dateInvestor
Stage · Construction startWe wrześniu 2023 r. została zawarta i uruchomiona umowa z generalnym wykonawcą. Prace budowlane ruszyły w grudniu 2023 r.
Current dateprzewidywany termin oddania jednostki do eksploatacji wyznaczony jest na III kwartał 2027 r.
InvestorBudowany przez PAK CCGT – spółkę pośrednio zależną od ZE PAK – blok gazowo-parowy CCGT w Turku
- iTurek.net30 Sep 2026Status
StatusObecnie na placu budowy prowadzone są m.in. prace związane z montażem chłodni wentylatorowej oraz budową pompowni wody chłodzącej.
- Energetyka2418 Dec 2025Funding
FundingUmowa podpisana z konsorcjum banków dotycząca kredytu długoterminowego opiewa na kwotę 2,15 mld zł.
- Parkiet5 Jan 2026