Energystrategic

Baltica 3 offshore wind farm

plannedstage: permits

Baltica 3 is the second phase of the Baltica offshore wind farm in the Polish Baltic, with a planned capacity of approx. 1045 MW, implemented by the PGE Baltica company as part of a joint venture of PGE and Ørsted (50 percent each). The farm is to be built in the part of the Baltic between Łeba and Ustka, at least 25 km from the shore. The project holds a location decision, an environmental decision and permits for connection infrastructure, but a final investment decision (FID) has not been taken for it. Commissioning was originally planned for 2026. In October 2025 PGE Baltica said the project had been suspended at one point and was undergoing deep economic optimisation, and that the company would like to return to the contracting phase as soon as possible. In May 2026 Ørsted confirmed that Baltica 3 was still in the optimisation phase and that further decisions on the project's future depend on market, regulatory and investor conditions. No current source gives a commissioning date, so the record assigns none.

How it went

Assessment: too early to assess, as of 1 Sep 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section

Deliverynot yet due[2]

Timeline

  1. Original date2026

Significance

Baltica 3, as the second phase of the Baltica complex (together with Baltica 2, approx. 2.5 GW), is to add approx. 1045 MW of installed capacity in offshore wind energy, supporting Poland's energy transition and the diversification of generation sources in the Baltic. Separating the investment decision from Baltica 2 shifted this phase in time relative to the original plans, and after the project was suspended and put through economic optimisation its schedule remains unresolved.

Sources 11 · 9 independent · 9 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. Pulsarowy.pl
    InvestorOriginal date
    InvestorProjekty Baltica 2 i Baltica 3 realizowane są przez PGE Baltica w partnerstwie joint venture z duńską firmą Ørsted
    Original dateUruchomienie pierwszego etapu projektu Morskiej Farmy Wiatrowej Baltica, czyli Baltica 3 o mocy ok. 1045 MW, planowane jest zgodnie z harmonogramem na 2026 roku.
  2. offshoreWIND.biz30 Jan 2025
    StatusDelivery
    Status · DeliveryBaltica 3 is planned to be fully operational by the end of the decade.
  3. Wizja Lokalna
    Stage
    Stagebudowa infrastruktury przyłączeniowej MFW Baltica-3 – lądowa stacja transformatorowa
    LocationBaltica, której udziałowcami są PGE i Ørsted, powstanie w części Bałtyku między Łebą a Ustką.
  4. Baltica (PGE / Orsted)
  5. PGE Baltica
  6. Funding
    Fundingwydane decyzje dotyczą dwóch projektów PGE i duńskiego Orsteda - Baltica 2 o mocy 1498 MW, oraz Baltica 3 o mocy 1045 MW
  7. Funding
    FundingFor each of the stages of the Baltica OWF (stages Baltica 2 and Baltica 3), there is one tranche to be disbursed in the Project Finance formula in the amount of up to EUR 350 million and one tranche to be disbursed based on guarantees from financial institutions
  8. Funding
    Funding50:50 joint venture partnership
  9. Bankier.pl (depesza ISBnews)1 Oct 2025
    StatusStage
    StatusProjekt swego czasu został wstrzymany, dzisiaj poddawany głębokiej optymalizacji ekonomicznej.
    StageChcielibyśmy z tym projektem jak najszybciej wrócić do fazy kontraktacji, korzystając z szans, które widzimy, że otwierają się na rynku dostaw dla morskiej energetyki wiatrowej
  10. Bankier.pl (depesza ISBnews)14 May 2026
    Current date
    Current dateProjekt Baltica 3 jest nadal na etapie optymalizacji.