Modernization of the regulatory structures of the border Oder
A project of the State Water Holding Polish Waters (Państwowe Gospodarstwo Wodne Wody Polskie) consisting of the reconstruction of the regulatory structures of the border section of the Oder: the renovation of 171 groynes (transverse dams), the construction of 21 new ones, and the execution of bank reinforcements. The aim was to improve navigation and ice-breaking conditions and to achieve a transit depth allowing class III waterway status. The co-financing agreement was signed on 3 December 2020, and the principal works were completed on 21 February 2024. The investment was co-financed from the Operational Programme Infrastructure and Environment (POIiŚ) and the World Bank.
How it went
Assessment: provisional, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 2 carry no assessment yet, one has an assessment with no confirmed quote. How to read this section
- Current
- odcinek graniczny sklasyfikowany jako KL II; 29.08.2025 RZGW Szczecin wstrzymał sondowania z powodu bardzo niskich głębokości tranzytowych (2025-10)
- Capacity or target
- III klasa (1,80 m)
Timeline
- Announced3 Dec 2020
- Original date2023
- Delivery21 Feb 2024
Change history
- 21 Feb 2024stage: operational
- 3 Dec 2020stage: announced
Significance
The reconstruction of the regulatory structures of the border Oder was intended to improve navigability and the effectiveness of winter ice-breaking on a key cross-border section of the river. The scope (renovation of 171 groynes, construction of 21 new ones, and bank reinforcements) was carried out as planned, and the principal works were completed on 21 February 2024. The implementation, however, became the subject of dispute over the rule of law and environmental protection: after the ecological disaster on the Oder in 2022, the Provincial Administrative Court (WSA) in Warsaw (December 2022) and the Supreme Administrative Court (NSA) (March 2023) ordered the works to be halted following complaints from Brandenburg and environmental organizations, yet the works were continued and brought to completion. After the investment was completed, on 27 January 2025 the Provincial Administrative Court in Warsaw annulled the environmental decisions of the RDOŚ and GDOŚ on the basis of which the works had been carried out; in the court's view, this means that the works were performed illegally. Brandenburg sued Poland, and environmental organizations are demanding the renaturalization of the river. The target transit depth of 1.80 m for a class III waterway on the border section of the Oder was not confirmed by an independent measurement after the completion of the works.
Sources 8 · 7 independent · 7 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Ministerstwo Infrastruktury3 Dec 2020CostInvestorAnnouncedOriginal dateFunding
CostKoszt realizacji projektu wynosi 470 mln zł.
Investor · AnnouncedPaństwowe Gospodarstwo Wodne Wody Polskie podpisało 3 grudnia 2020 r. umowę
Original dateZakończenie inwestycji jest planowane w pierwszej połowie 2023 roku.
LocationPlanowane prace wykonywane będą na wysokości Słubic i Gozdowic.
FundingDofinansowanie w ramach POIiŚ to 211,6 mln zł.
- PGW Wody Polskie - RZGW w Szczecinie8 Aug 2024StatusStageDeliverySignificance
Status · DeliveryZasadnicze prace realizowane w ramach projektu zostały zakończone 21 lutego 2024 roku.
StageDla wszystkich zrealizowanych odcinków uzyskano pozwolenia na użytkowanie wykonanych obiektów - ostatni odcinek uzyskał pozwolenia na użytkowanie 27 marca 2024 roku.
SignificanceInwestycja na Odrze Granicznej obejmowała remont 171 ostróg, budowę 21 nowych oraz wykonanie umocnień brzegowych.
- Teraz ŚrodowiskoMar 2023Significance
SignificanceMamy dowody na to, że mimo wyroku NSA, Wody Polskie oraz ich podwykonawcy kontynuują prace
- OKO.press22 Dec 2022
- [5]1B.2 Prace modernizacyjne na Odrze granicznej w celu zapewnienia zimowego lodołamania ↗archived ✓Biuro Koordynacji Projektu Ochrony Przeciwpowodziowej Dorzecza Odry i Wisły2024
- OKO.press28 Jan 2025Assessment
AssessmentW momencie wydania wyroku z 27 stycznia mleko jest już rozlane. Prace, które uznano za przeprowadzone nielegalnie, wykonano.
AssessmentWyrok jest nieprawomocny, strony mogą się jeszcze od niego odwołać.
- PGW Wody Polskie - RZGW we Wrocławiu / RZGW w Szczecinie3 Oct 2025
- [8]Wody Polskie analizują konsekwencje uchylenia przez sąd decyzji środowiskowych dla prac na Odrze ↗archived ✓PortalMorski.pl29 Jan 2025