← all projects
⚡Energystrategic

Modernisation of the Porąbka-Żar Pumped-Storage Power Plant

pausedstage: constructionover budget
PLN 1.3 billion
contract value · data from Jan 2025incl. VAT≈ PLN 1.3 billion (value-by-stage, est., nominal)funding: multilateral development bank, National Recovery PlanThe amount is the value of the contract for the technological part (four hydro units with installations) after the indexation annex (aneks waloryzacyjny) of January 2025; originally PLN 1.12 billion gross. It excludes the separate task of modernising the upper reservoir and the waterway (PLN 203.38 million net). PGE withdrew from the contract in December 2025.

The modernisation programme of the Porąbka-Żar pumped-storage power plant in Międzybrodzie Bialskie (Śląskie Voivodeship), the only underground power plant in Poland and the country's second-largest pumped-storage plant, with a capacity of 540 MW. The investor is PGE Energia Odnawialna of the PGE group. The programme covers the replacement of four hydro units with their auxiliary installations and the modernisation of the upper reservoir on top of Mount Żar, the water intakes and the tunnels. The technological part was awarded on 22 July 2022 to a consortium of GE Hydro France and Mostostal Warszawa for PLN 1.12 billion gross; an indexation annex of January 2025 raised the contract value by 15%, to PLN 1.29 billion gross. Work on site began in May 2024 with the draining of the upper reservoir, and the replacement of the turbine units was scheduled to start in October 2024. Operation of the four new units was planned for early 2028. In December 2025 PGE Energia Odnawialna withdrew from that contract, citing among other things delay and the impossibility of completing the investment on time, charged contractual penalties (PLN 4.72 million and PLN 105.33 million) and demanded repayment of an unsettled advance of PLN 151.59 million. In April 2026 Mostostal Warszawa started arbitration against its consortium partner. A separate task, the modernisation of the upper reservoir and the waterway (planned cost PLN 203.38 million net), was carried out by general contractors led by Polish firms, and in July 2026 PGE Energia Odnawialna signed a KPO loan of PLN 152.64 million for it.

How it went

Assessment: provisional, as of 20 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, one carries no assessment yet, 2 have an assessment with no confirmed quote. How to read this section

Budgetover budget[1]

Timeline

  1. Announced1 Oct 2020
  2. Construction startMay 2024
  3. Original date2027

Change history

  • Dec 2025status: pausedPGE Energia Odnawialna withdrew from the technological-part contract with the GE Hydro France and Mostostal Warszawa consortium.
  • May 2024status: in progressDraining of the upper reservoir and start of the modernisation works.
  • May 2024stage: construction
  • 1 Oct 2020stage: announced

Significance

After the modernisation the plant's capacity is to remain unchanged, but its operational efficiency is to increase: the hydro units are to be adapted to long-term operation in compensation mode and to need repairs less often. The investor points to adapting the installation to the needs of the capacity market, the energy market and system services, and to extending the plant's service life. The withdrawal from the technological-part contract in December 2025 left the replacement of the hydro units without a contractor, and the further course of the modernisation has not been announced.

Sources 9 · 7 independent · 6 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. WNP.pl22 Dec 2025
    CostBudgetInvestor
    CostZaktualizowana wartość umowy wynosiła 1,29 mld zł brutto.
    BudgetNa początku stycznia 2025 r. zawarto aneks do umowy, zwiększający jej wartość o kwotę w wysokości 168,99 mln zł brutto, co stanowiło 15 proc. wartości pierwotnego kontraktu.
    InvestorPGE Energia Odnawialna, spółka z grupy PGE, naliczyła kary umowne i odstąpiła umowy z konsorcjum GE Hydro France i Mostostal Warszawa
    LocationElektrownia wykorzystuje jako zbiornik dolny Jezioro Międzybrodzkie, którego zapora znajduje się w Międzybrodziu Bialskim w woj. śląskim, natomiast górny zbiornik (całkowicie sztuczny) wybudowany jest na szczycie góry Żar.
  2. Gramwzielone.pl29 Dec 2025
  3. Portal Samorządowy29 Dec 2025
    Funding
    FundingPGE Polska Grupa Energetyczna i Europejski Bank Inwestycyjny zawarły umowę kredytową o wartości 2,25 mld zł, z której pieniądze zostaną przeznaczone m.in. na sfinansowanie modernizacji Elektrowni Szczytowo-Pompowej Porąbka-Żar
  4. tuzywiec.pl31 Dec 2025
  5. elektro.info6 Jun 2024
    StageConstruction start
    StageObecnie w ESP Porąbka Żar trwa remont zbiornika górnego, w związku z tym niezbędne było odstawienie elektrowni i opróżnienie zbiornika w okresie od 1 maja do 30 września 2024 roku.
    Construction startniezbędne było odstawienie elektrowni i opróżnienie zbiornika w okresie od 1 maja do 30 września 2024 roku
  6. Energetyka241 Oct 2020
    AnnouncedOriginal date
    AnnouncedNależąca do Grupy Kapitałowej PGE spółka PGE Energia Odnawialna ogłosiła dwa postępowania przetargowe związane z modernizacją Elektrowni Szczytowo Pompowej Porąbka – Żar.
    Original datePlanowana modernizacja - która w przypadku zbiornika zakończy się do końca 2024 r. a w części technologicznej do końca 2027 r.
  7. Inwestycje.pl20 Jul 2026
    Funding
    FundingCałkowity planowany koszt realizacji przedsięwzięcia wyniósł 203,38 mln zł netto, natomiast wartość przyznanego finansowania to 152,64 mln zł.
  8. WNP.pl3 Apr 2026
    Status
    StatusW grudniu 2025 r. spółka PGE Energia Odnawialna odstąpiła od umowy zawartej z konsorcjum firm - GE Hydro France i Mostostal Warszawa oraz naliczyła kary umowne.
  9. Beskidzka24.pl30 Dec 2025