Energystrategic

Baltica 2 Offshore Wind Farm

under constructionstage: construction
30 bn PLN
estimate · data from 17 Jun 2026net or gross: not recorded≈ 30 bn PLN (value-by-stage, est., nominal)funding: PGE finances its 50% share on a project-finance basis: PLN 11.1bn (approx. EUR 2.6bn) in loans from 24 Polish and international financial institutions, including the European Investment Bank and the European Bank for Reconstruction and Development, approx. PLN 6bn in loans from Bank Gospodarstwa Krajowego, of which PLN 5.5bn from the National Recovery Plan (KPO), 25-year inflation-protected contract for difference (CfD) with the Polish state; Ørsted finances its half itself

An offshore wind farm with a capacity of 1.5 GW being built in the Polish part of the Baltic Sea, about 40 km from shore off Ustka, in a 50/50 partnership between PGE Polska Grupa Energetyczna and Denmark's Ørsted. The project comprises 107 Siemens Gamesa turbines of 14 MW each, mounted on monopiles (111 monopiles in total, including 4 for offshore electrical substations). The final investment decision was taken on 30 January 2025, the first foundations were installed at sea in May 2026, and full commissioning is planned by the end of 2027. The cost of the investment is estimated in the media at about PLN 30 billion; PGE is financing its half in a project finance formula, including with PLN 11.1 billion in loans from 24 institutions and about PLN 6 billion from BGK (including PLN 5.5 billion from the National Recovery Plan), and the project has a 25-year contract for difference with the Polish state.

How it went

We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Construction startJan 2025
  2. Original date2027
  3. Current date2027

Change history

  • 30 Jan 2025stage: construction

Significance

Once fully operational, Baltica 2 is to be the largest offshore wind farm in Poland, capable of supplying green electricity for about 2.5 million Polish households. The project is one of the largest energy undertakings currently under way in the country and a key element in the development of offshore wind power in the Polish Baltic.

Sources 8 · 7 independent · 8 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. offshoreWIND.biz30 Jan 2025
    FundingOriginal date
    Fundingobtained PLN 11.1 billion (approximately EUR 2.6 billion) in loan from 24 Polish and international financial institutions, including European Investment Bank and European Bank for Reconstruction and Development
    Funding25-year inflation-protected contract for difference (CfD) in place with the Polish state
    Original dateBaltica 2 is expected to be fully commissioned by the end of 2027
    FundingAccording to PGE, the Baltica 2 offshore wind project obtained PLN 11.1 billion (approximately EUR 2.6 billion) in loan from 24 Polish and international financial institutions, including European Investment Bank and European Bank for Reconstruction and Development.
    FundingLocated approximately 40 kilometres off the Polish coast near Ustka, Baltica 2 has a 25-year inflation-protected contract for difference (CfD) in place with the Polish state.
  2. BalticWind.EU30 Jan 2025
    StageStage historyFundingConstruction start
    Stage · Stage historyFID allows for official transition from the project development to construction phase of the offshore wind farm.
    FundingA total of about PLN 6 billion will come in form of loans from Bank Gospodarstwa Krajowego from which PLN 5.5 billion coming from the National Recovery Plan.
    Construction startPGE and Ørsted have already started building the onshore connection infrastructure.
  3. Evertiq20 May 2026
    StatusInvestor
    StatusThe first foundations have been successfully installed in the Polish part of the Baltic Sea.
    Investorbuilt, owned and operated in a 50/50 partnership between Ørsted and Polish energy company PGE Polska Grupa Energetyczna
    Locationlocated approximately 40 km off the Polish coast near Ustka
  4. WNP.pl17 Jun 2026
    CostCurrent date
    CostKoszt tej inwestycji sięgnie 30 mld zł.
    Current datepełne uruchomienie komercyjne planowane jest do końca 2027 roku
  5. BalticWind.EU9 Jan 2025
  6. Windtech International30 Jan 2025
  7. Funding
    FundingØrsted finances its part of the project from its own capital.