The largest onshore wind farm in Poland, spread across the border of the Pomorskie and Zachodniopomorskie voivodeships, approximately 9 km from the Baltic shore. In the first stage, 81 General Electric turbines with a combined capacity of 219 MW were commissioned; after a further expansion, completed in March 2023, the complex grew to 98 turbines and approximately 257 MW of installed capacity. The investor is Potęgowo Mashav, owned by the Israeli fund Mashav; the construction was co-financed by, among others, the European Bank for Reconstruction and Development.
How it went
This record carries no outcome assessment on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.
Timeline
- DeliveryMar 2023
Change history
- Mar 2023status: completedCompletion of the third, final stage of the farm's expansion.
- Mar 2023stage: operational
- Dec 2020stage: operational
Significance
With a capacity on the order of 257 MW, the complex is the largest onshore wind installation in the country and one of the larger facilities of its kind in Europe, significantly increasing the national potential for generating energy from onshore wind. The farm surpassed the previous leader – the Margonin farm (approximately 120 MW) – in capacity and became a benchmark for the scale of onshore wind power in Poland.
Sources 5 · 5 independent · 3 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- Gramwzielone.pl2019CostInvestorFunding
Costcałkowity koszt inwestycji wyniesie 1,25 mld zł
Investorspółkę Potęgowo Mashav Sp. z o.o. należącą do izraelskiego funduszu Mashav
Locationfarma wiatrowa o mocy 219 MW, która powstała na terenie powiatów słupskiego w woj. pomorskim i sławieńskiego w woj. zachodniopomorskim, w minimalnej odległości 9 km od linii brzegowej Morza Bałtyckiego
Fundingkredyt w wysokości 209 mln zł na budowę farmy wiatrowej Potęgowo przyznał Europejski Bank Odbudowy i Rozwoju
- Mashav EnergiaStatusDelivery
Status · DeliveryMashav finalised the construction of the third stage of Potęgowo wind farm in March 2023.
- BiznesAlert.pl3 Dec 2020Stage
StageUrząd Regulacji Energetyki (URE) wydał koncesję największej farmie wiatrowej w Polsce, która jest zlokalizowana w woj. pomorskim i zachodniopomorskim.
- Funding
FundingKonsorcjum pięciu banków: Europejski Bank Odbudowy i Rozwoju (główny aranżer), DNB Bank Polska S.A. (agent), Bank Pekao S.A. (wyłączny dostawca kredytu VAT), a także mBank i Intesa Sanpaolo