An onshore wind farm being built by TAURON Zielona Energia in Rawicz County (Wielkopolskie Voivodeship). The installation is to consist of 53 turbines with a rated capacity of 3.6 MW each and a height of 134 m, giving a target capacity of approximately 190 MW. Once completed, it is to be the largest wind investment of the TAURON Group and the second-largest onshore wind farm in Poland. The project was purchased in 2024, and its completion was scheduled for the second half of 2027. By August 2025 the foundations for all 53 turbines had been poured.
How it went
This record carries no outcome assessment on any of the four axes yet. The timeline and sources below show what is known about it; the assessment itself has not been made.
Timeline
- AnnouncedSep 2024
- Original date2027
- Current date2027
Change history
- Aug 2025status: in progressFarm under construction – foundations poured for all 53 turbines; work ongoing on assembly yards, roads and electrical substations.
- Aug 2025stage: construction
Significance
The target capacity of approximately 190 MW from 53 turbines is to cover the demand of nearly 200 thousand households and make the farm the largest wind investment of the TAURON Group as well as the second-largest onshore wind farm in Poland after Potęgowo. The investment significantly increases national onshore wind generation capacity and shifts the balance of the state-owned group's renewables portfolio toward wind power.
Sources 6 · 3 independent · 4 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- TAURON Polska Energia (biuro prasowe)24 Sep 2024CostOriginal dateCurrent date
CostCałkowity koszt ma wynieść niespełna 2 mld zł
Original date · Current daterealizacja tego projektu zakończy się w drugiej połowie 2027 roku
LocationFarma wiatrowa Miejska Górka zlokalizowana będzie w powiecie rawickim, w województwie wielkopolskim
- TAURON Zielona EnergiaInvestor
InvestorTAURON Zielona Energia sp. z o.o.
- Biznes PAP24 Sep 2024Announced
AnnouncedTauron kupił projekt farmy wiatrowej Miejska Górka o mocy docelowej ok. 190 MW
- [4]TAURON buduje jedną z największych farm wiatrowych w Polsce. Fundamenty dla 53 turbin są już gotowe ↗archived ✓TAURON Polska Energia (biuro prasowe)27 Aug 2025StatusStage
Statuspodczas budowy wylano fundamenty dla wszystkich, 53 nowoczesnych turbin wiatrowych
StageZakończyliśmy prace związane z betonowaniem fundamentów. Obecnie kontynuowane są działania przy budowie placów montażowych, dróg dojazdowych, linii kablowych oraz stacji elektroenergetycznych
- Funding
FundingGrupa TAURON zawarła z Europejskim Bankiem Inwestycyjnym umowę kredytu o wartości 1,12 mld zł.
- Inżynieria.com (portal branżowy Inżynieria)22 Apr 2026Current date
Current dateZakończenie inwestycji planowane jest na pierwszą połowę 2027 r.