Energystrategic

Młoty Pumped-Storage Power Plant (revival)

in preparationstage: permits
5.0 bn PLN
estimate · data from Jan 2026net or gross: not recorded≈ 5.0 bn PLN (value-by-stage, est., nominal)

The revival of the Młoty pumped-storage power plant in the Bystrzyckie Mountains, on the Bystrzyca Łomnicka river, in the village of Młoty in the Bystrzyca Kłodzka municipality in Kłodzko County (Dolnośląskie Voivodeship). Construction began in 1973 and was abandoned; the project is being taken up again by PGE Polska Grupa Energetyczna, carrying it out through the special-purpose company PGE Inwest 12, in which NFOŚiGW holds a 49% stake. Under the current assumptions, the plant is to reach a capacity of 1,050 MW and approx. 4,090 MWh of storage capacity. The estimated cost of the investment is approx. PLN 5 billion (some sources give at least PLN 6 billion). Carrying out this variant of the project requires flooding the entire village of Młoty to create the lower reservoir. At the turn of 2025 and 2026 the company submitted an environmental report to the Regional Directorate for Environmental Protection (RDOŚ) in Wrocław, and the project schedule depends on the timing of obtaining the environmental decision.

How it went

We have assessed this project, but none of the four axes is shown here: 3 carry no assessment yet, one has an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. Original date2030

Change history

  • Dec 2025stage: permits
  • Jul 2024stage: permits

Significance

The project is intended to be one of the most advanced undertakings to build a pumped-storage power plant in Poland and to serve for energy storage and stabilisation of the national power system during peaks in demand. At full capacity of 1,050 MW the installation could operate for approx. four hours. The lower reservoir on the Bystrzyca river is also to serve a retention function, reducing the risk of flooding in the area of Bystrzyca Kłodzka. The price of the undertaking, however, is the flooding of the entire village of Młoty to create the lower reservoir, which raises social opposition and environmental concerns.

Sources 7 · 7 independent · 7 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. AgroNews12 Jan 2026
    Stage historyCost
    Stage historyNa dzień przed końcem roku spółka złożyła wymagany dokument
    Costkoszt inwestycji wyniesie ok. 5 mld zł
  2. Gramwzielone.pl2 Jun 2025
    StatusInvestor
    StatusJak podaje PGE, harmonogram projektu uzależniony jest od terminu uzyskania decyzji środowiskowej.
    InvestorFundusz został udziałowcem (49%) spółki celowej PGE Inwest 12.
  3. Forsal.pl30 Apr 2025
  4. wywlaszczenie.pl15 Jan 2025
    Stage
    StageW lipcu 2024 r. inwestor wystąpił o decyzję środowiskową
    LocationDolnym Śląsku w powiecie kłodzkim
  5. Money.pl10 Nov 2024
    Original date
    Original datePierwotny harmonogram przewidywał, że będzie gotowa w 2030 r.
  6. Funding
    FundingW ramach umowy NFOŚiGW obejmie 49 proc. udziałów w spółce celowej PGE Inwest 12, odpowiedzialnej za budowę ESP Młoty. PGE zachowa większościowy pakiet udziałów - 51 proc.
  7. Funding
    FundingFundusz ma objąć 49 proc., a PGE 51 proc. udziałów w spółce celowej PGE Inwest 12