← all projects
Energystrategic

Ostrołęka C Power Plant (coal unit)

cancelledstage: constructionrestructuredabandonedaudit finding or investigation
6.0 bn PLN
contract value · data from Apr 2018incl. VAT≈ 6.0 bn PLN (value-by-stage, est., nominal)

Ostrołęka C Power Plant is an abandoned project for a 1,000 MW coal-fired unit in Ostrołęka, carried out by a special-purpose company owned in equal shares by the state-owned groups Energa and Enea. Works formally began at the end of December 2018, but in February 2020 the partners suspended financing and abandoned the coal variant, earmarking the site for a separate combined-cycle gas unit. Inspectors from the Supreme Audit Office (NIK) judged the way the investment was closed to be flawed and announced a notification to the prosecutor's office.

Why it failed

In February 2020 the partners Energa and Enea suspended financing for the construction of the Ostrołęka C coal unit and subsequently abandoned the coal variant in favour of gas technology; Enea withdrew from the undertaking. A NIK audit assessed the way the project was closed as unlawful and uneconomical, pointing to a loss exceeding PLN 1.3 billion.

How it went

Assessment: settled, as of 15 Jul 2026. This is our reading, not a verdict, and we show it only where a quote from a source listed below stands behind it. Of the four, 3 carry no assessment yet. How to read this section

Deliverynot delivered[6]
Scopesuperseded[8]
Lossesaudit finding or investigation · 1.3 bn PLN[8]

Timeline

  1. Construction start28 Dec 2018
  2. Original date2023

Change history

  • Feb 2020status: cancelledIn February 2020, Energa and Enea suspended financing for construction of the coal-fired Ostrołęka C unit, and in June 2020 they ultimately abandoned the coal variant. The elements of the unit already built were dismantled in March 2021, and the prepared site was designated for a successor combined-cycle gas (CCGT) unit built by Orlen.
  • 28 Dec 2018stage: construction

Significance

Halting one of the last large domestic coal investments produced a loss estimated by NIK at over PLN 1.3 billion, comprising write-downs by Energa and Enea and a settlement with the general contractor reaching approx. PLN 958 million net. The matter became the subject of a critical NIK report and a notification to the prosecutor's office, and the site where work had begun was later used for a gas unit project.

Sources 10 · 8 independent · 5 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. BiznesAlert20 May 2020
  2. WNP.pl18 Aug 2025
    StatusInvestorFailure descriptionFunding
    StatusW lutym 2020 r. inwestorzy, czyli Energa i Enea, zawiesili finansowanie projektu Ostrołęka C.
    InvestorDziałania zarządu spółki Elektrownia Ostrołęka związane z wycofaniem się z budowy bloku węglowego Ostrołęka C
    Failure descriptionW lutym 2020 r. inwestorzy, czyli Energa i Enea, zawiesili finansowanie projektu Ostrołęka C
    Failure descriptionw wyniku realizacji inwestycji bezpowrotnie utracono ponad 1,3 mld zł
    FundingW grudniu 2018 r. Enea deklarowała zaangażowanie w wysokości 1 mld zł, a Energa co najmniej 1 mld zł.
  3. Interia Biznes
    StatusOwner type
    Statusjuż w lutym 2020 r. Enea i Energa poinformowały o zawieszeniu finansowania projektu
    Owner typepo 50 proc. udziałów miały państwowe koncerny energetyczne Enea i Energa
  4. TVN2418 Aug 2025
  5. WNP.pl29 Dec 2018
    StageConstruction start
    Stage · Construction startSpółka Elektrownia Ostrołęka 28 grudnia wydała polecenie rozpoczęcia prac
  6. Politechnika Warszawska24 Apr 2022
    StatusOriginal dateDelivery
    Status · DeliveryW 2020 r. zadecydowano o rezygnacji z budowy 1000 MW bloku węglowego
    Original dateplanowano zakończyć budowę w drugiej połowie 2023 r .lub na początku 2024 r.
    Locationgeneralny wykonawca kontraktu na budowę bloku węglowego w Ostrołęce
  7. Interia BiznesApr 2018
    Cost
    CostZwycięska oferta konsorcjum GE Power i Alstom ma wartość 5,05 mld zł netto, czyli 6,023 mld zł brutto.
  8. Najwyższa Izba Kontroli (NIK)18 Aug 2025I/24/004/KST
    ScopeLosses
    ScopeDo rozbiórki powstałych już elementów bloku węglowego Ostrołęka C. doszło w marcu 2021 r., po tym, jak zapadła decyzja, że zostanie tam zbudowany blok gazowo-parowy i że zamiast węgla do produkcji energii elektrycznej wykorzystywany będzie gaz ziemny.
    Lossesw wyniku realizacji inwestycji bezpowrotnie utracono ponad 1,3 mld zł
    LossesW związku z ustaleniami kontroli NIK przygotowuje zawiadomienie do prokuratury o podejrzeniu popełnienia przestępstwa polegającego na wyrządzeniu znacznej szkody majątkowej spółce Elektrownia Ostrołęka
  9. ZielonaGospodarka.pl
  10. eOstroleka.pl23 Mar 2026
    Losses
    LossesŚledztwo w sprawie budowy elektrowni Ostrołęka C zostało przedłużone do 21 września