CCGT Grudziądz gas-and-steam power plant (Unit I, 563 MW)
The CCGT Grudziądz gas-and-steam unit (Unit I) with a net capacity of approx. 563 MW, built by the company CCGT Grudziądz of the Energa Group (Orlen Group). The general contractor under the EPC formula is a consortium of Metlen (formerly Mytilineos) and Siemens Energy. The value of the investment is approx. PLN 2 billion. The cornerstone was laid in May 2023, and the original commissioning date (2025) was postponed to 2026. In 2026 the unit entered the start-up phase and delivered energy to the national power grid for the first time.
How it went
We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section
Timeline
- Original date2025
- Current date2026
Change history
- Jul 2026stage: commissioning
- 18 May 2023stage: construction
Significance
The new unit increases the dispatchable, flexible generation capacity of the national system (operating in the range from just under 40% to 100% of capacity), supporting the balancing of the system amid a growing share of renewables and replacing high-emission coal capacity. The unit is covered by capacity-market support (a capacity obligation of 518 MW from 2026).
Sources 8 · 8 independent · 6 archived
Every fact on this card comes from the sources below. Next to each source – which fields it supports.
Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.
- wGospodarce.pl18 May 2023Stage history
Stage historyObecnie na terenie budowy prowadzone jest palowanie, a także zbrojenie i wylewanie płyt fundamentowych.
- Metlen Energy & MetalsInvestorOriginal date
InvestorSPV CCGT Grudziądz Sp z o.o. (owned entirely by Energa S A, part of Orlen Group)
Original date38 months after the signing of the contract
LocationGrudziadz, Poland
- CCGT Grudziądz Sp. z o.o.8 Jan 2026
- Inwestycje.pl13 Jul 2026StatusStageStage history
Status · StagePierwszy zapłon turbiny gazowej oraz synchronizacja generatora z krajową siecią elektroenergetyczną to kluczowe etapy rozruchu bloku gazowo-parowego.
Stage historyenergia z CCGT Grudziądz po raz pierwszy trafiła do systemu
- [5]CCGT Grudziądz blisko rozruchu. Już w przyszłym roku będzie pracować pełną parą i gazem ↗archived ✓Zawsze Pomorze11 Jul 2025SignificanceCost
Name563 MW netto
Significancemogący pracować w zakresie od niespełna 40% do 100% mocy z zachowaniem wszystkich standardów emisyjnych
CostWarty ok. 2 mld zł blok gazowo-parowy w Grudziądzu zasilany będzie wysokometanowym gazem ziemnym.
- WysokieNapiecie.pl2026Current date
Current dateBloki CCGT w Grudziądzu i Ostrołęce ruszą w I poł. 2026, być może w I kw. 2026
- Funding
FundingPKN ORLEN S.A. zobowiązał się w Porozumieniu do pokrycia do 100% nakładów inwestycyjnych związanych z realizacją Projektu, ale nie więcej niż 1,8 mld zł, pod warunkiem zawarcia przez spółkę CCGT Grudziądz Sp. z o.o. (spółka celowa realizująca Projekt) umowy mocowej.
- [8]bankier.pl ↗Funding
FundingBlok ma obowiązek mocowy w wysokości 518 MW, począwszy od 2026 r.