Żarnowiec Battery Energy Storage System (BESS, 262 MW / 981 MWh)

under constructionstage: construction
1.6 bn PLN
contract value · data from Mar 2025incl. VAT≈ 1.6 bn PLN (value-by-stage, est., nominal)funding: KPO

A large-scale battery energy storage system with a capacity of 262 MW and approximately 981 MWh, being built by PGE Polska Grupa Energetyczna in Pomorskie Voivodeship, adjacent to the Żarnowiec pumped-storage power plant. The general contractor is LG Energy Solution Wrocław, and the contract value is PLN 1.555 billion gross. Construction was inaugurated in March 2025; by July 2026, more than 150 of the 204 battery units had been installed and a power transformer delivered. Completion is planned for 2027, and the project benefits from support under the National Recovery Plan.

How it went

We have assessed this project, but none of the four axes is shown here: 2 carry no assessment yet, 2 have an assessment with no confirmed quote. The timeline and sources below show what is known about it. How to read this section

Timeline

  1. AnnouncedJul 2022
  2. Construction start24 Mar 2025
  3. Original date2027
  4. Current date2027

Change history

  • 24 Mar 2025stage: construction
  • 21 Jul 2022stage: announced

Significance

Once completed, it is set to be the largest battery energy storage facility in Poland and one of the largest in Europe. The installation is intended to support the integration of renewable energy sources and the stabilization of the national power system; the project secured a 17-year contract in the capacity market auction for 2029, as well as Poland's first permit promise (promesa koncesji) for electricity storage.

Sources 7 · 4 independent · 6 archived

Every fact on this card comes from the sources below. Next to each source – which fields it supports.

Independence is counted the same way the gate that admits a record counts it: subdomains and titles from one publisher are a single voice, Wikipedia is zero. That is why the number is lower than the number of links. Three is the minimum.

  1. LG Energy Solution Wrocław7 Mar 2025
    CostOriginal dateInvestorFunding
    CostWartość umowy wyniosła 1,555 mld zł brutto.
    Original dateZakończenie budowy przewidziane jest na drugi kwartał 2027 roku.
    InvestorPGE Polska Grupa Energetyczna zawarła umowę z LG Energy Solution Wrocław
    LocationBateryjny magazyn energii w Żarnowcu będzie zlokalizowany w województwie pomorskim, w pobliżu największej w Polsce Elektrowni Szczytowo Pompowej Żarnowiec
    FundingWcześniej, w grudniu ub.r. uzyskał on 17-letni kontrakt w aukcji rynku mocy na rok 2029.
  2. LG Energy Solution Wrocław25 Mar 2025
    StageConstruction start
    Stage · Construction startPodczas wydarzenia w warszawskiej Elektrowni Powiśle oficjalnie zainicjowano budowę Magazynu Energii Żarnowiec
  3. Energetyka246 Jul 2026
    StatusFunding
    StatusZamontowano już ponad 150 jednostek DC-Link, a w najbliższym czasie mają ruszyć prace rozruchowe.
    FundingInwestycja jest realizowana przy wsparciu środków z Krajowego Planu Odbudowy.
  4. Gramwzielone.pl6 Jul 2026
    Current date
    Current dateWedług harmonogramu instalacja zostanie oddana do użytku w 2027 roku.
  5. Gramwzielone.pl21 Jul 2022
    Announced
    AnnouncedPolska Grupa Energetyczna uzyskała od Urzędu Regulacji Energetyki promesę koncesji na magazynowanie energii elektrycznej w wielkoskalowym elektrochemicznym magazynie energii
  6. Funding
    FundingNa realizację tej inwestycji PGE otrzyma ponad 477 mln zł dofinansowania z KPO.